Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
Rules of Construction for the Tenant’s Construction Works
in Bangladesh Special Economic Zone (“Rules of Construction”)
1. Purposes
1.1. This Rules of Construction is supplemental regulations to the Internal Regulations (‘’ Internal
Regulations ’’) of Bangladesh Special Economic Zone, and to apply for any and all the Tenant’s
construction works in Bangladesh Special Economic Zone.
1.2. Purpose
• To prevent damage for Common Areas and Facilities of BSEZ from the Tenant’s construction
works.
• To notify the contractors to comply with the rules and regulations set forth by BSEZ.
1.3. The Tenant and its contractors shall comply with the Internal Regulations of Bangladesh Special
Economic Zone as referred to this Rules of Construction.
2. Construction Kick-Off Meeting, Construction Inspection and Monitoring by BSEZ
2.1. BSEZ has a right to hold the Construction Kick-Off Meeting in order to coordinate between
BSEZ, the Tenant and its contractors for the Tenant’s construction works. Representatives of
the Tenant and its contractors shall attend the Construction Kick-Off Meeting.
2.2. BSEZ may hold the construction inspection randomly within the construction stage. The
purpose of this inspection is to inspect whether the Tenant and its contractors are complying
with this Rules of Construction or not. BSEZ will announce to the Tenant and its contractors for
the inspection 3 calendar Days in advance.
2.3. BSEZ may monitor and patrol all construction sites’ activities of Bangladesh Special Economic
Zone every day. If the Tenant and its contractors violate this Rules of Construction, BSEZ shall
take the action as follows:
(i) Issue the “Remind Letter” to the Tenant and its contractors for taking necessary actions.
(ii) Issue the “Suspension Letter” to the Tenant’s construction work if the Tenant and its
contractors do not take the necessary actions immediately after received the “Remind
Letter” from BSEZ or violate this Rule of Construction again.
3. Security and Safety Management
3.1. The Tenant and its contractors shall take responsibility for security and safety management of
their construction works. The Tenant and its contractors shall make efforts to ensure safety and
security of the Lot as per their own safety rules and regulations.
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
3.2. The Tenant and its contractors shall not take rest, stand by, eat, drink and smoke outside of the
Lot. The Tenant and its contractors shall prepare a canteen or place to eat and drink, smoking
area for construction workers. The Tenant and contractors shall prohibit to drink alcoholic
beverages and to take illegal drugs for their staffs, workers and drivers in Bangladesh Special
Economic Zone.
3.3. The Tenant and its contractors shall submit emergency contact list to BSEZ during construction
works. The Tenant and its contractors shall take responsibility for their own emergency
response plan during construction works. In case any accidents happen during construction
period, the Tenant and its contractors shall inform to BSEZ immediately.
3.4. The Tenant and its contractors shall install the lightning arrestor or any other lightning protection
equipment in the Lot in accordance with any applicable laws and regulations in order to prevent
lightning accident during construction works.
3.5. The Tenant and its contractors shall follow the traffic rules to prevent traffic accident in
Bangladesh Special Economic Zone.
3.6. The Tenant and its contractors are prohibited to keep any animals and pets both inside and
outside of the Lot and not let to feed the dogs in order to prevent the rabies disease and to
avoid the dog bites. The Tenant and its contractor shall instruct all employees not let to feed
the dogs.
3.7. The Tenant and its contractors shall inform working time of construction to BSEZ in advance
and shall, at all times starting at the time commencement of its factory construction, provide
reliable and competent watchmen/security to guard the Lot and premises. In the event that
BSEZ at any time observed and deems the watchmen/security service is inadequate, the
Tenant and its contractors shall increase the number or change the watchmen/security to the
satisfaction of BSEZ.
3.8. FOR PUBLIC SAFETY: Whenever the activities of the Tenant and its contractors create a
condition hazardous to traffic or to the public safety inside Bangladesh Special Economic Zone,
the Tenant and its contractors shall furnish, at own expense such flagmen and guards as
necessary to give adequate warning to the public of any dangerous conditions to be
encountered. The Tenant and its contractors shall furnish, erect, and maintain fences,
barricades, lights, signs and avoid damage or injury to the public. Convenience of abutting lots
along the road shall be provided for, as far as practicable, Convenient access to driveways,
bunkhouses, and buildings along the line of work shall be maintained. The temporary
approaches to crossings or intersecting roads shall be kept clean and in good condition.
3.9. If in case, there is existing structure on the ground, and a temporary structure was built and
was about to be demolished for completion of the job, the use of explosives and heavy
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
demolition equipment is not allowed. The Tenant and its contractors shall exercise the utmost
care not to endanger life, property and the environment. Before any demolition operations are
started, the Tenant and its contractor shall furnish BSEZ as detailed plan, in writing, of
operations showing the method proposed for the prevention of damage to retain existing
structures. Besides, The Tenant and its contractors shall effectively control the noise emitting
from any source within the Lot with sound-absorbing materials or other suitable means, and
shall comply with the applicable laws or regulations of the People’s republic of Bangladesh
including not but limited to BNBC 2020 and ECR 1997 as updated or replaced from time to
time.
4. Common Areas and Facilities of BSEZ
4.1. The Tenant and contractors are strongly reminded to comply with Article 39.1 of the Internal
Regulations such as;
Should there be, at any time, any damage to or loss of any of BSEZ’s property in Bangladesh
Special Economic Zone including, but not limited to, any property belonging to or under the
control of BSEZ by any act of the Tenant, its contractor, its sub-contractor or its visitors, the
Tenant shall compensate all the costs and expense for remedy and restoration already paid by
BSEZ or the sufferer of the said damage/loss or shall remedy and restore the said property to
the original condition, to the satisfaction of BSEZ or the sufferer, by themselves. The method
and amount of such compensation shall be at BSEZ’s or the sufferer’s reasonable, fair and sole
discretion.
4.2. The Tenant and its contractors shall return the BSEZ properties including but not limited to,
interlocking block at the walkway, water meter, rainwater drainage manhole, wastewater
manhole, landscaping at the buffer zone and green area and others if the Tenant and
contractors relocate, destroy or remove it.
5. Protective Control during construction work
5.1. The Tenant and its contractors are strongly reminded to comply with Article 12.2.3, Internal
Regulations such as;
No excavation shall be made except in connection with the approved construction of the
Improvements and, upon completion thereof, exposed openings shall immediately be backfilled
and leveled. Any kind of excavation work in the buffer zone as specified in Article 1.14 must
have the prior approval from BSEZ and with BSEZ’s supervision during the work. Excavation
work in buffer zone must be done by the Tenant using manual labor or by other methods
provided that the Tenant shall exercise due care not to damage the underground utilities when
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
undertaking such excavation work. The Tenant shall compensate BSEZ for any damages or
losses to the underground utilities of BSEZ arising from the excavation works on the part of the
Tenant or its employees/agents.
5.2. The Tenant and its contractors shall confirm the location and depth of the existing underground
facilities in buffer zone (rainwater drainage pipelines, water supply pipelines, wastewater
pipelines, power cables, telecommunication lines and others) using manual labors only during
the connection works in order not to damage them. The Tenant and its contractors shall protect
or support existing underground facilities during construction works if necessary. The Tenant
and its contractors shall install the proper safety barrier around the construction activities at the
buffer zone and common area, then it shall be covered to all construction activities.
5.3. The Tenant and its contractor shall inform BSEZ before any excavation starts at buffer zone
and common area. BSEZ may monitor the excavation work.
5.4. The Tenant and its contractors shall assign the supervisor while the said excavation work starts.
The Tenant and its contractors shall inform immediately to BSEZ if there are found/observed
any deviation with BSEZ provided drawings.
6. Environmental Protective Controls
6.1. The Tenant and its contractors shall not discharge the wastewater to the outside of their Lot,
BSEZ’s rainwater drainage or BSEZ’s wastewater pipeline during construction works. The
Tenant and its contractors shall install septic tank or other proper facilities in construction site
and shall keep wastewater including kitchen water and toilet water in the septic tank. The
Tenant and its contractors shall arrange to collect the wastewater by authorized industrial waste
company and organization. The Tenant and its contractors shall protect septic tank to avoid
overflow to the ground or seep into underground by rainwater and wastewater.
6.2. The Tenant and its contractors shall install enough temporary toilets for all staffs, workers and
visitors in construction site.
6.3. The Tenant and its contractors shall not dispose their waste and garbage inside and outside of
BSEZ. The Tenant and its contractors shall arrange to collect waste and garbage, including but
not limited to, concrete debris, construction chemical, oil and grease, hazardous waste, light
bulb, paint, battery and others by authorized industrial waste company and organization.
6.4. The Tenant and its contractors shall keep a record of information of Pest/Insect control during
construction works such as supplier name, contact information, consumption of chemical,
specification of chemical (MSDS / Material Safety Data Sheet) which use for Pest/Insect control.
6.5. The Tenant and its contractors shall follow their Environmental Conservation and Prevention
Plan which was approved by BEZA OSS.
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
6.6. Tenant and contractors are strongly reminded to comply with Article 30.1, Internal Regulations
such as;
The Tenant shall effectively control the noise emitting from any source within the Lot with sound-
absorbing materials or other suitable means and shall comply with the applicable laws or
regulations of the People’s republic of Bangladesh including not but limited to BNBC 2020 and
ECR 1997 as updated or replaced from time to time.
6.7. The Tenant and its contractors are strongly reminded to comply with Article 32.2 of the Internal
Regulations such as;
As for vibration control, the Tenant shall have its own arrangement to satisfy with the applicable
laws or regulations of the People’s republic of Bangladesh. The Tenant shall have its own
arrangement, if necessary, such as installing Vibration Control Devices for equipment that will
require such devices if its plant operations produce ground vibrations that can be felt at a point
one (1) meter inward from any property line of its Lot. The Tenants and its contractors shall also
hold liable for any damage or claim by any third party including, but not limited to neighbors,
neighboring premises, the residents in surrounding areas and the relevant authorities due to
any noise and vibration impacts.
6.8. The Tenant and its contractors shall also hold the liable for any damage or claim by any third
party including but not limited to neighbors, neighboring premises, the residents in surrounding
areas and the relevant authorities due to any noise and vibration impacts.
6.9. The Tenant and its contractors shall set up the proper plan for the dust control during the
construction activities.
7. Internal Roadways, Parking, Temporary Entrance/Exit and Access Road
7.1. The Tenant and its contractors are strongly reminded to comply with Article 18.1 of the Internal
Regulations such as;
On-street parking without permission of BSEZ is strictly prohibited within Bangladesh Special
Economic Zone. The Tenant shall take full responsibility for its visitors, contractors and
employees. Any vehicle parked on the street without permission shall be removed at BSEZ’s
sole discretion without prior notice and all costs involved in removal shall be compensated by
the relevant Tenant(s).
7.2. The Tenant and its contractors shall keep clean the Internal Roadways of BSEZ. The Tenant
and its contractors shall install car washing area inside their Lot and make clean all vehicles
before leaving from their Lot. The Tenant and contractors shall implement preventive measures
to avoid making the Internal Roadways and Common Areas and Facilities dirty. The Tenant and
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
its contractors shall clean up Internal Roadways and Common Areas and Facilities if they make
it dirty.
7.3. The Tenant and its contractors shall inform the location of the temporary entrance, exit and
route of the access road that they will mainly use when they get approval for the Temporary
Preparation Works or start of construction from BSEZ. If necessary, the Tenant and its
contractors shall strengthen the Buffer Zones which contain utilities of BSEZ, manholes,
walkways and box culverts so as not to damage the areas when the vehicles pass on top.
7.4. BSEZ has a right to change the route of access road in case of necessity for the maintenance
work, repairing work or construction work by BSEZ.
7.5. Passenger cars can pass through BSEZ permanent roads. For the avoidance of doubt, any
tractors which are used for the purpose of transportation for any passengers can’t be accepted
to pass through BSEZ permanent roads.in addition, normal construction vehicles including not
but limited to cement mixers, trailers, truck cranes can be accepted to pass through BSEZ
permanent roads in accordance with the instruction from BSEZ with prior notification to BSEZ.
7.6. It is strictly prohibited any kind of heavy machineries / vehicles including not but limited to
tractors, wheel loaders, caterpillar tracks to pass through BSEZ permanent roads. In case any
damage to the permanent roads and/or related facilities occurs due to the passage of above
vehicles belonging to the Tenant and/or its contractors, all the cost of repair shall be borne by
the Tenant sorely.
8. Prior to Start of Construction
8.1. Project Information Board
Before start of construction works, the Tenant and its contactors shall install project information
board including the Tenant name, Lot Number, Main contractor name and Sub-contractor name.
Information to be included and installation method shall be in accordance with Article 10 of this
Rules of Construction.
8.2. Temporary Preparation Works
The Tenant and its contractors may start their temporary preparation works before design
approval from BSEZ refer to the Article 10 of the Internal Regulations. The Tenant and its
contractors shall apply ‘’Application for Temporary Preparation Work’’ (including letter of
attorney (if any), layout plan of temporary preparation work, detail drawings, copy of this Rules
of Construction with signature and contact Information) to BSEZ in advance. The temporary
preparation work means installing temporary hoardings, preparing temporary offices and
constructing temporary accesses for construction works. If there is any change of the layout
plan of temporary preparation work, the Tenant and its contractors shall submit to BSEZ 7
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
(seven) calendar days in advance.
8.3. Soil Investigation and Survey Works
The Tenant and its contractors may conduct (1) soil investigation for boring and soil quality
works and (2) survey work for lot boundary and elevation before design approval from BSEZ
refer to the Article 10 of the Internal Regulations. The Tenant and its contractors shall apply
‘’Application for Soil Investigation and Survey Work’’ (including general layout plan/ location
map/ first schedule, bore hole location plan (if Soil Investigation for Boring), time schedule and
contact information) to BSEZ 7 (seven) calendar days in advance.
8.4. Permanent Fence Works
The Tenant and its contractors may start construction works for permanent fence along the lot
boundary after design approval from BSEZ refer to the Article 10 of the Internal Regulations.
The Tenant and its contractors shall apply ‘’Application for Start of Permanent Fence Work’’
(including letter of attorney (if any), master plan, detail drawing of permanent fence,
construction work schedule, copy of Insurance for construction, copy of this Rules of
Construction with signature and Contact information) to BSEZ 7 (seven) calendar days in
advance. The Tenant and its contractors shall comply with Article 19 of the Internal Regulations
for Fence construction work.
8.5. Piling Works
The Tenant and its contractors may start piling work after design approval from BSEZ refer to
the Article 10 of the Internal Regulations and before approval of start of construction from BSEZ.
The Tenant and its contractors shall apply ‘’Application for Start of Piling Work’’ (including letter
of attorney (if any), copy of temporary commencement of construction from BEZA or relevant
authority if any, copy of insurance for construction works, copy of this Rules of Construction
with signature) to BSEZ 7 (seven) calendar days in advance.
8.6. Material Storage
The Tenant and its contractors shall set up the proper material storage area inside the Lot. The
Tenant and its contractors shall not put all materials especially roofing materials at roof top in
order not to fly. The Tenant and its contractors shall place the iron related materials under the
shelter or cover with the waterproof sheets in order to avoid the contact of rainwater in the rainy
season.
8.7. Setback Lines
The Tenant and its contractors shall comply with Article 14 of the Internal Regulations of setback
lines. No structure, no construction or no installation of machinery and equipment shall be
permitted within setback lines. However, some structures and improvements (which are
stipulated in Article 14.2 of the Internal Regulations) are excluded from these setback provisions.
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
9. Start of Construction
9.1. The Tenant and its contractors shall get approval from BSEZ for start of construction before
they commence it. The Tenant and its contractors shall apply ‘’Application for Start of
Construction’’ (including letter of attorney (if any), copy of fire safety certificate from BEZA OSS,
copy of building permit from BEZA OSS, copy of environmental conservation and prevention
plan approval from BEZA OSS, copy of insurance for construction works, copy of this Rules of
Construction with signature and other permits from related authority if required) to BSEZ 10
(ten) calendar days in advance. The Tenant and its contractors shall comply with Article 12,of
the Internal Regulations for commencement of construction.
9.2. If there is any change of the approved design, the Tenant and its contractors shall get approval
from BSEZ before they commence it. The Tenant and its contractors shall apply “Application
for Design Change/Modification” (including letter of attorney (if any), design
change/modification application format with explanatory diagram, old design with BSEZ stamp,
design change/modified drawing and any document that BSEZ may require) to BSEZ 7 (seven)
calendar days for minor design change and 21 (twenty-one) calendar days for major design
change in advance.
9.3. The Tenant and its contractors shall maintain the insurance of construction with All Risks
including third party liability during the construction period.
10. Temporary Hoardings
10.1. In accordance with Article 8.1 of this Rules of Construction, prior to the construction works, the
Tenant and its contractors shall install temporary hoardings including the Tenant name, Lot
Number, Main contractor name and Sub-contractor name, inside of the Tenant’s site boundary.
In addition, the Tenant and its contactors shall install notification board which describe
construction site safety and cleaning such as excavation work by manual labor only, clean and
wash the vehicles before leaving the site, prohibition to drink alcoholic beverages and illegal
drugs and others and contract numbers for emergency in order to notify safety and cleaning to
staffs, workers, drivers and visitors (In English and Bangla).
10.2. BSEZ has a right to order to push back the temporary hoardings into the Lot in case of necessity
for the maintenance work, repairing work or construction work in buffer zone by BSEZ.
10.3. The temporary hoardings shall be in good quality, and it shall be maintained in good
appearance. The temporary hoardings shall cover the scenery of construction works from
outside boundary of the Lot.
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
10.4. The Tenant and its contractors shall execute all construction works within the temporary
hoardings. The Tenant and its contractors shall get approval from BSEZ if they will use outside
of the temporary hoardings.
10.5. The Tenant and its contractors may install permanent fence instead of temporary hoardings
refer to Article 8.4 of this Rules of Construction. In that case, the Tenant and its contractors
shall cover the surface of the permanent fence by mesh net or others during construction works
of permanent fence.
11. Water Well
11.1. The Tenant and its contractors are strongly reminded to comply with Article 24.1 of the Internal
Regulations such as;
The Tenant must not establish any water wells or similar facilities on any portion of the Lot and
shall only use water supplied through BSEZ’s common water supply pipeline.
12. Rainwater Drainage
12.1. The Tenant and its contractors shall comply with Article 25 of the Internal Regulations of
rainwater drainage system.
12.2. The Tenant and its contractors shall construct temporary rainwater drainage in their Lot during
rainy season in order not to overflow rainwater into the Internal Roadways and the Common
Areas and Facilities before constructing permanent rainwater drainage. The Tenant and its
contractors shall properly and cleanly enclose and maintain temporary rainwater drainage
within the Lot. The Tenant and its contractors shall not dump any garbage, leftover food and
etc. into the temporary rainwater drainage. BSEZ’s drainage facilities shall be cleaned if these
are being dirty by the construction activities of the Tenant and its contractors. In addition, in
order not to overflow sand and/or soil from their Lot to the Common Areas, the Tenant and its
contractors shall prepare the necessary improvement such as sandbag along with boundary
and entrance area, and in case the sand and other materials are overflowed from the Lot to the
Common Areas, the Tenant and its contractors shall have sole responsibility for cleaning the
Common Areas in timely manner.
12.3. The Tenant and its contractors shall get approval from BSEZ for commencement of rainwater
drainage connection work before they commence it. The Tenant and its contractors shall apply
‘’Application for rainwater drainage connection work commencement’’ (including general layout
plan, rainwater drainage layout plan, detail drawing of rainwater drainage connection point and
schedule of connection work) to BSEZ 7 (seven) calendar days in advance. BSEZ shall carry
out 4 (four) times inspection ((1) (one) Before excavation and indication of location for
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
excavation on the ground, (2) After completion of excavation, (3) Before backfilling and (4) After
completion of restoration).
12.4. Tenant and its contractors shall never discharge rainwater to BSEZ’s wastewater discharge
pipeline.
13. Water Supply
13.1. The Tenant and its contractors shall comply with Article 24 of the Internal Regulations of water
requirements.
13.2. The Tenant and its contractors shall get approval from BSEZ to start the water supply pipeline
connection work before they commence it. The Tenant and its contractors shall apply
‘’Application for Water Supply Pipeline Connection Work Commencement’’ (including general
layout plan, water supply layout plan, detail drawing of water supply connection point and
schedule of connection work) to BSEZ 7 (seven) calendar days in advance. BSEZ shall carry
out 4 (four) times inspection ((1) Before excavation and indication of location for excavation on
the ground, (2) After completion of excavation, (3) Before backfilling and (4) After completion of
restoration).
13.3. The Tenant and its contractors shall get approval from BSEZ to start using water supply before
they use it. The Tenant and its contractors shall apply ‘’Application for Start of Water Supply’’ to
BSEZ 7 (seven) calendar days in advance.
14. Wastewater discharge
14.1. The Tenant and its contractors shall comply with Article 28 of this Internal Regulations of
wastewater.
14.2. The Tenant and its contractors shall get approval from BSEZ to start the wastewater discharge
pipeline connection work before they commence it. The Tenant and its contractors shall apply
‘’Application for Wastewater Discharge Pipeline Connection Work Commencement’’ (including
general layout plan, wastewater discharge pipeline layout plan, detail drawing of wastewater
connection point and schedule of connection work) to BSEZ 7 (seven) calendar days in
advance. BSEZ shall carry out 4 (four) times inspection ((1) Before excavation and indication
of location for excavation on the ground, (2) After completion of excavation, (3) Before
backfilling and (4) After completion of restoration).
14.3. The Tenant and its contractors shall get approval from BSEZ to start the wastewater discharge
before discharging. The Tenant and its contractors shall apply ‘’Application for Start of
Wastewater Discharge’’ to BSEZ 7 (seven) calendar days in advance. In addition, the Tenant
and its contractors shall complete the whole internal wastewater system before discharging to
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
BSEZ wastewater pipeline as well. BSEZ shall carry out one-time inspection before the
commencement of discharging.
15. Power Supply
15.1. The Tenant and its contractors shall get approval from BSEZ to start the power line connection
work before they commence it. The Tenant and its contractors shall apply ‘’Application for
Power Line Connection Work’’ (including power line layout plan, detail drawing of power line
connection point and schedule of connection work) to BSEZ 7 (seven) calendar days in
advance. BSEZ shall carry out 4 (four) times inspection ((1) Before excavation and indication
of location for excavation on the ground, (2) After completion of excavation, (3) Before
backfilling and (4) After completion of restoration).
15.2. The Tenant and its contractors shall get approval from BSEZ to shut down the BSEZ’s power
supply for the power line connection work with BSEZ’s power supply facilities such as
Disconnection Switch (DS) or Ring Main Unit (RMU). the Tenant and its contractors shall apply
‘’Application for Power Shut Down’’ to BSEZ minimum 30 (thirty) calendar days in advance.
Power shut down date shall be basically on Friday or National Public Holiday only.
15.3. The Tenant and its contractors shall get approval from BSEZ for energizing before they
energize it. The Tenant and its contractors shall apply ‘’Application for energizing’’ to BSEZ 7
(seven) calendar days in advance. BSEZ may request the presence of BSEZ member when
the Tenant energize.
16. Telecommunication
16.1. The Tenant and its contractors shall get approval from BSEZ to start the telecommunication
line connection work before they commence it. The Tenant and its contractors shall apply
‘’Application for Telecommunication Line Connection Work’’ (including telecommunication
layout plan, detail drawing of telecommunication line and schedule of connection work) to BSEZ
7 (seven) calendar days in advance. BSEZ shall carry out 4 (four) times inspection ((1) Before
excavation and indication of location for excavation on the ground, (2) After completion of
excavation, (3) Before backfilling and (4) After completion of restoration).
16.2. The Tenant and its contractors shall get approval from BSEZ to start using the
telecommunication line before they use it. The Tenant and its contractors shall apply
‘’Application for Start of Telecommunication Line” to BSEZ 7 (seven) calendar days in advance.
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
17. Removal of Earth
17.1. The Tenant and its contractors are strongly reminded to comply with Article 12.2.6 of the Internal
Regulations such as;
(a) The Tenant shall not fill up the Lot from earth outside of Bangladesh Special Economic
Zone without the prior written approval of BSEZ.
(b) The Tenant shall not make holes or puddles or lowlands by digging in the Lot, unless the
Tenant has an inevitable technical reason to do so and obtains the prior written approval of
BSEZ.
(c) The Tenant shall not carry out any earth, sand clay from the Lot. However, BSEZ may
allow the Tenant to move earth from the Lot to the place designated by BSEZ at its sole
discretion.
17.2. The Tenant and its contractors shall get approval from BSEZ for removal of earth from the Lot.
The Tenant and its contractors shall apply ‘’Application for removal earth from the Lot” (including
volume of earth and schedule of removal of earth) to BSEZ 30 (thirty) calendar days in advance.
17.3. The Tenant and its contractors shall follow BSEZ’s supervision at the designated earth storage
area. The Tenant and its contractors shall remove earth, sand clay only and shall not remove
construction waste such concrete debris or garbage and others. The Tenant and its contractors
shall show tenant name and the lot number in front of the trucks for removal of earth. The
Tenant and its contractors shall arrange the access way and spreading for the earth at the
designated earth storage area.
17.4. The Tenant and its contractors shall set up the prevention plan in order not to make the road
dirty along the way from the Lot to the designated earth storage area.
17.5. The Tenant and its contractors shall reserve enough temporary storage area for excess earth
in order to store them until the designated earth storage area is available.
17.6. The Tenant and its contractors are recommended not to carry out the earth within rainy season
since the risk of road dirt.
18. Completion Inspection
18.1. The Tenant and its contractors shall get approval for completion of construction works from
BSEZ. The Tenant and its contractors shall apply ‘’ Application for Completion Inspection’’
(including copy of “Building Completion Certificate”, necessary documents from BEZA OSS, As
built drawing, copy of liability insurance cover note for operation stage, copy of environmental
inspection record from BEZA OSS and EIA or DOE approval (if required), copy of approval of
start of use for water supply, wastewater discharge, telecommunication line usage, power
Bangladesh SEZ Ltd. Sonpara, Panchrukhi Via Rupganj Araihazar, Narayanganj-1460
energizing, electrical inspection certificate from BEZA OSS/ BSEZ and other permits from
authority if any.) to BSEZ for inspection.
18.2. BSEZ shall conduct inspection after receipt of complete and sufficient application. BSEZ shall
approve only after the Tenant and its contractors rectified or remedied the items which BSEZ
points out during the inspection.
Received and Acknowledged by: