Site Restoration Plan
Upon completion of the geotechnical soil investigation, all temporary facilities, equipment,
materials, and associated installations will be removed from the site. The borehole locations and
surrounding areas will be restored to a safe, clean, and orderly condition.
The following restoration measures will be implemented:
1. Removal of Equipment and Temporary Facilities
All drilling rigs, water pumps, water storage tanks, hoses, temporary toilet facilities,
tools, materials, and other temporary installations will be completely removed from the
site.
2. Borehole Restoration
Upon completion of the required soil investigation and sampling, the boreholes will be
properly sealed and backfilled in accordance with the applicable geotechnical and
environmental requirements. Suitable approved material will be used for backfilling, and
the material will be placed and compacted appropriately to prevent settlement or the
creation of open voids.
3. Bentonite Slurry and Waste Restoration
Any bentonite slurry, drilling mud, and other drilling-related waste generated during the
investigation will be collected in designated containers or temporary containment areas to
prevent uncontrolled discharge into the surrounding ground, drainage system, or water
bodies. After completion of the drilling activities, the remaining bentonite slurry and
drilling waste will be removed from the BSEZ premises and transported to an appropriate
and approved disposal location in accordance with BSEZ requirements and applicable
environmental regulations. No bentonite slurry or drilling waste will be discharged
directly onto the ground, into drains, or into nearby water bodies.
4. Ground Surface Restoration
Any disturbed ground surrounding the borehole locations, equipment areas, or access
routes will be levelled and reinstated as far as practicable to its original condition. Any
temporary surface damage caused during the investigation will be repaired.
5. Removal of General Waste and Debris
All general waste, including plastic bags, used gloves, packaging materials, and other
debris generated during the investigation, will be collected and removed from the site on
a daily basis. No waste will be left within the project area after completion of the work.
6. Restoration of Water Collection Areas
Following completion of the investigation, all water pumps, pipelines, storage tanks, and
associated temporary arrangements used for water collection and supply will be removed.
The water collection point and surrounding area will be cleaned and restored to a neat
condition.
7. Final Site Cleaning and Inspection
A final cleaning and inspection will be conducted to ensure that no equipment, waste,
bentonite slurry, temporary structures, or hazardous materials remain at the site. Any
identified damage or disturbance will be addressed before demobilization.
The site will be handed back in a clean, safe, and orderly condition, fully restored as far as
practicable, and in accordance with the requirements and instructions of BSEZ.