Lide Bangladesh Textile Technology Co., LTD.
Answer of the Query of BB - for Application for Soil Investigation of Lide Bangladesh Textile
Technology Co., LTD.
1. Work Schedule: As discussed in the meeting, Lide Bangladesh (LBTT) san mentioned that
they would start the work the day after receiving approval. Please include the working days in
the schedule. If LBTT san are unable to meet the submitted schedule, they should provide a
revised schedule accordingly.
Answer:
Start date: Around 14th September, 2026, depend on the date of entrance approval. Usually, once
BSEZ approval issued, we will mobilize in within two days at most.
Ending date:28th September, 2026.
Duration: 15 days
2. Drawing: The locations of the workers’ washroom, smoking zone, resting shelter, etc. should
be clearly identified in the drawing, along with their dimensions and other relevant details. A
designated area for waste storage should also be clearly indicated in the layout.
See the attachment: "Layout Dawing"
Answer:
See the attachment: "Layout Drawing"
3. Site Access: The method of moving equipment and vehicles to the tenant’s plot should be
clearly described in the WMS. If any vehicle is parked on our road, proper barricading will be
required.
Answer:
The soil investigation equipment will be transported to the site by truck. The truck will be parked on
BSEZ Road 7, in front of the project plot.The equipment will then be manually mobilized from the
truck into the project plot using manual handling/head loading.
Appropriate barricading, traffic management, and other necessary safety measures will be provided
and maintained in accordance with the requirements and instructions of BSEZ
throughout the equipment mobilization and soil investigation activities.
4.Water Supply: The WMS should explain how sufficient water will be provided and managed
throughout the work.
Answer:
Daily Water Requirement
Approximately 6 – 7 m³ per day (for drilling two boreholes daily).
Lide Bangladesh Textile Technology Co., LTD.
Water Collection Plan
Source: Canal at the nearest point to Lide Bangladesh.
Equipment:
One diesel pump (2 – 3 inch) at canal side, placed on a plastic spill-proof sheet to prevent oil leakage.
Water will be pumped to the site via hoses, with 2 – 3 intermediate tanks (3 m³ each) for relay transfer
( depend on the actual pump pressure, may not use).
At the site, two 3 m³ tanks will be placed near each borehole for drilling use.
Pollution and cleanliness Control:
All pumps will be placed on plastic sheets to prevent diesel spills.
After each water collection session, all hoses and equipment in public areas outside our plot will be
promptly removed to avoid any disruption to other activities within the park.
The team will handle equipment carefully and clean up the area after each operation.
Collection Time:
Maximum two sessions per day, total ≤ 60 minutes, as requested.
Total On-Site Storage Capacity:
6 m³ (two 3 m³ tanks), covering daily demand.
Schedule
Start date: Around September 14, 2026, depend on the date of your entrance approval. Usually, once
your approval issued, we will mobilize in within two days at most.
Duration: 15 days
Water will be needed throughout the entire drilling period.
5. Borehole Locations: The locations of the boreholes, including the dimensions/ coordinates,
should be indicated in the drawing/WMS.
Answer:
See the attachment: "Soil Test Point"
6. Safety & PPE: The required safety and PPE arrangements should be clearly described in the
WMS.
Answer:
We will strictly comply with all relevant safety regulations of the park. All personnel entering the site
will be required to wear appropriate PPE, including safety helmets, high-visibility vests, and safety
shoes, in accordance with the park's requirements.
Lide Bangladesh Textile Technology Co., LTD.
7. Waste Management: Plastic bags, used gloves, and other waste materials should be removed,
and the site will be cleaned on a daily basis. This should be mentioned in the WMS.
Answer:
All waste generated during the soil investigation activities, including plastic bags, used
gloves,packaging materials, and other general waste, shall be collected and removed from the work
areaon a daily basis. The site shall be cleaned and maintained in a neat and orderly
conditionthroughout the entire investigation period.
For the temporary toilet facility, a bucket-based waste collection system will be adopted.
Humanexcreta will be collected in a designated, securely covered container and removed from
theBSEZ premises on a daily basis for proper disposal at an approved location, in accordance with the
applicable BSEZ requirements and environmental and sanitation regulations.
No waste, sewage, or human excreta shall be discharged or disposed of within the project site, on the
access road, or into the surrounding drainage system or water bodies.
8. Restoration: Please confirm in the WMS that the site will be restored to its original condition
and that all boreholes will be properly backfilled with soil after completion of the work.
Answer:
See the attachment: "Restoration"
9. Manpower and Vehicle List: Please share the manpower and vehicle lists.
Answer:
See the attachment: "List of Man power and Vehicles for Geotechnical Investigation 1"