3 rd August 2026
Lide Bangladesh Textile Technology
Ltd. – BSEZ
Kick off Meeting
Today’s Agenda
🄫 2026 Bangladesh SEZ Ltd. 1
1.Temporary works & approvals
2. Design Approval
3. Building Permit
4. Commencement of Construction
5. Infrastructure Connection Concept
6. Q&A session
Exhibit 2 [Approvals to start Temporary works ]
🄫 2026 Bangladesh SEZ Ltd. 2
If all submissions are okay, BSEZ would provide approval within next 7 calendar days upon receiving each application
BC - Common Fence Design - facing the internal road)
🄫 2026 Bangladesh SEZ Ltd. 3
Today’s Agenda
🄫 2026 Bangladesh SEZ Ltd. 4
1.Temporary works & approvals
2. Design Approval
3. Building Permit
4. Commencement of Construction
5. Infrastructure Connection Concept
6. Q&A session
🄫 2026 Bangladesh SEZ Ltd. 5
Exhibit 2 [Design Approval by BSEZ]
1. DAA Process shall start at least two months prior the Factory construction
2. The Investor must obtain Design Approval from BSEZ Prior applying for Building permit to BEZA
6 🄫 2026 Bangladesh SEZ Ltd.
Location BEZA SRO-46 Internal Regulation
of BSEZ
Internal roadways 12 meter 15 meter
Neighbouring lot 3.5 meter 6 meter
Tenant shall comply with following guidelines during design consideration
⚫ BSEZ Internal Regulation
⚫ BEZA SRO no- 46
⚫ BNBC
⚫ Other regulations from relevant authorities
In case of some regulation BSEZ is more stringent compared to BEZA
guidelines. An example is given below-
Setback restriction
Design approval by BSEZ
General Concept of BSEZ design approval
The Tenant must comply with the Article 14- Setback lines of BSEZ Internal Regulation
Design Approval by BSEZ
7 🄫 2026 Bangladesh SEZ Ltd.
The Tenant must submit the detail drawings in line with the Design Approval Cheklist.
10. Design Approval from BSEZ (“Design Approval”)
10.1 Submission of Design Approval Application
The Design Approval Application (“ DAA ”), accompanied by the items listed in Exhibit 2,
shall be submitted by the Tenant to BSEZ prior to start of construction activity. Plans
stipulated in 10.1 should be submitted to BSEZ not later than two (2) months before the
start of factory construction.
2026_Required Drawing List for DAA_Final (002).pdf
8 🄫 2026 Bangladesh SEZ Ltd.
Design approval by BSEZ (Land Description)
Setback-
⚫ 15m from internal roadways
⚫ 6m from neighboring plot
Design approval by BSEZ (Layout of Lide Bangladesh)
🄫 2026 Bangladesh SEZ Ltd. 9
Final- 28 th June 2026
🄫 2022 Bangladesh SEZ Ltd. 10
Design approval by BSEZ (Layout of Lide Bangladesh)
Today’s Agenda
🄫 2026 Bangladesh SEZ Ltd. 11
1.Temporary works & approvals
2. Design Approval
3. Building Permit
4. Commencement of Construction
5. Infrastructure Connection Concept
6. Q&A session
12 🄫 2026 Bangladesh SEZ Ltd.
Land Use
Permit
Building
Permit
(1) Procedures
(2) Required Documents for Land Use permit (Tentative)
⚫ Application Form (FORM-BP-01-A).
⚫ Location and plot map of EZ.
⚫ Land Use Plan (which is showing position of building, internal road, green area,
setback line, gate and gate house, Fence and other facilities)
⚫ Utility Connection Plan (connection route of Electricity, Water, Sewage, Rainwater,
Fence & others).
⚫ Other documents and drawings required by BEZA-OSS
→ Expected timeline is 7 working days for Land Use Permit.
Building Permit Process
13 🄫 2026 Bangladesh SEZ Ltd.
⚫ Application Form (FORM-BP-02-A)
⚫ Architectural Drawing
⚫ Structural Analysis
⚫ Electrical Plan
⚫ Mechanical and Plumbing Plan
⚫ Copy of Approved Firefighting floor Plan (NOC)
⚫ Information of Licensed Engineers/ Architects (FROM-BP-02-B)
⚫ Engineer’s confirmation on compliance of BNBC Code
⚫ Copy of ECC (Green & Orange-A, B category) or Copy of EIA approval (Red
category)
⚫ e-data of all documents and drawings by PDF format
⚫ Other documents and drawings required by BEZA-OSSC
The tenants are encouraged to consult with BEZA prior applying for Building permit.
(2) Required Documents for Building Permit (Tentative)
→ Expected timeline is 30 working days for Building Permit.
→ Before proceeding to BP, Tenants must complete BSEZ DAA process!!
Design approval by BSEZ [Building Permit]
Today’s Agenda
🄫 2026 Bangladesh SEZ Ltd. 14
1.Temporary works & approvals
2. Design Approval
3. Building Permit
4. Commencement of Construction
5. Infrastructure Connection Concept
6. Q&A session
15 🄫 2026 Bangladesh SEZ Ltd.
Exhibit 2 [Construction Approval by BSEZ]
→ Upon obtaining the Building Permit, the tenant shall apply to BSEZ for construction
approval
Today’s Agenda
🄫 2026 Bangladesh SEZ Ltd. 16
1.Temporary works & approvals
2. Design Approval
3. Building Permit
4. Commencement of Construction
5. Infrastructure Connection Concept
6. Q&A session
All Utility Plot C15
🄫 2022 Bangladesh SEZ Ltd. 17
18
Design approval by BSEZ (3D View of Buffer Zone)
🄫 2026 Bangladesh SEZ Ltd.
19
Design approval by BSEZ (3D View of Buffer Zone)
🄫 2026 Bangladesh SEZ Ltd.
20
Design approval by BSEZ (3D View of Connection points)
🄫 2026 Bangladesh SEZ Ltd.
21 🄫 2026 Bangladesh SEZ Ltd.
Design approval by BSEZ (Water connection)
22 🄫 2026 Bangladesh SEZ Ltd.
5. Design approval by BSEZ (Power connection)
23
Tenants Power Connection Flowchart
SL
No
Action Items Actual Process Execution party Timeline
BSEZ Tenant BREB PBS OCEI FSCD BEZA
1 Application EA-
Registration
1. As per Exhibit 2; E-EA tenant will submit the Load demand
2. Drawing of Power Supply including Layout plan, Exhibit drawing, Single line
diagram, metering panel drawing, SLD of the metering panel detail.
3. BSEZ will share the feedback to Teanant if any update require
● N/A
1.1 Submission-
Detail of Power facility
● ● 3
2 Receiving NOC for the design from
BREB
1. BSEZ will share the design of Tenant with BREB for providing the NOC
2. BREB will review the drawing, share if any modification required
3. BREB will provide the NOC /consent for the drawing
● ● 21
3 NOC by BSEZ [Reply of EA] 1. Upon receipt of NOC from BREB; BSEZ will issue NOC as reply of submitted
EA.
● 1
4 Application of
Power Connection Work (DD)
1. Tenant will apply for Power connection work to BSEZ;
2. Include the power line layout plan, detail drawing of power line connection point
and schedule of connection work, WMS of connection work and Pole based
modification
● N/A
4.1 Power Connection Charge Tenant shall submit the payment of connection charge to BSEZ before
commencement of work.
● N/A
4.2 Approval of power connection work
(DD)
Upon payment completion, review of submissions; specially WMS and BSEZ's
confirmation; BSEZ will issue the Approval to Tenant to start the Connection
work.
● 1
2.1 Testing metering CT&PT 1. Tenant will submit the application for the testing to BSEZ and BSEZ will
forward to PBS
2. PBS will inform the date of testing and Tenant PIC shall bring the CT&PT to
BREB lab
3. Upon completion of test, Tenant PIC will collect the CT&PT test report from
PBS
● ● ● 7
5 Shutdown request of 33kV line (LOTO)
for the construction work
1. Tenant shall apply LOTO in the format of BSEZ at least 7 days prior to the
installation work on the pole.
2. Tenant shall comply and align with BSEZ during the inspections of LOTO
procedure. 3. BSEZ will turnoff the line for the power
connection work of tenant
● ● 1
6 Application of Energizing (ED, ED-A); In line with Exhibit 2, E-ED
Tenant shall apply for Energizing attaching all submissions to BSEZ
● N/A
6.1 Submissions attachments;
ED, ED-A
Included but not limited to;
1. OCEI Approval
2. FSCD Effectiveness Certificate and others as stipulated in ED-A
● ● N/A
● ● ● N/A
6.2 Meter Installation Upon receipt of Application ED, ED-A with submission and in parallal to review,
BSEZ shall inform tenant of IOT Meter Installation, as per BSEZ's schedule and
install the meter
● 1
7 Power Agreement BSEZ will share Agreement to tenant for tenenats check and specific information
as instructed by BSEZ
. Upon both parties check and input, BSEZ and Tenant will sign on Agreement
● ● 2
8 Approval of the power Energization;
ED-Energizing
At this stage BSEZ will issue official Approval and inform tenant of the schedule
of Energizing
. Tenant shall inform their Electrical contractor and vendor to be present
. BSEZ will monitor and maintain LOTO as per the previous LOTO provided to
Tenant
. Any additional information and instruction will be shared with Tenant based on
actual scenario
● 1
Comprehensive Stage (Exhibit 2 - Article A, B, C D, E)
🄫 2026 Bangladesh SEZ Ltd. 24
Stage SL Action Items Authority
Prior to
Commencement of
Construction
1 Temporary Preparation Approval** BSEZ
2 Initial Layout Check by BSEZ BSEZ
3 Land USE Plan BEZA
4 Design Approval by BSEZ ** ★ BSEZ
5 Environment Clearance (Department of Environment) DoE
6 No Objection Certificate (Fire Service Civil Defence) FSCD
7 Building Permit ★ BEZA
8 Other Approval (if necessary) -
9 Construction Approval by BSEZ** BSEZ
Commencement of
Construction to
Commercial Operation
10 Utility Connection Approvals from BSEZ** BSEZ
11 Fire License & Fire Effectiveness Certificate FSCD, BEZA
12 Occupancy Certificate BEZA
13 Trial Production (if necessary) BEZA
14 Commercial Certificate BEZA
15 Construction Completion Inspection ** ★ BSEZ
* Critical Pass ★
** As per BSEZ Exhibit 2 **
→ Summary of Construction stage in line with Exhibit 2 & Internal Regulation of BSEZ
🄫 2026 Bangladesh SEZ Ltd.
Thank you very much