[cover1]
SANYO ENGINEERING & CONSTRUCTION INC.
BANGLADESH BRANCH ADDRESS: BDBL BHABAN, 6th Floor, Plot #3, Bir-Uttam A.K. Khandakar Road,
Mohakhali C/A, Dhaka-1212, Bangladesh Tel: +88-029843361 Fax: +88-029843360
Our Ref : SEC/BD/161112/00 | 12th November, 2016
SHIMIZU CO., LTD.
Unit 2301, 23rd Floor, Empire Tower 195 South Sathorn Road,
Yannawa, Sathorn, Bangkok 10120, Thailand
Attn : | M&E GENERAL MANAGER
Mr. MIMURA
RE: | YKK BANGLADESH FACTORY
Additional and Cancel Lighting Work at Office Building
Dear Sir,
We refer to the above and are pleased to submit our offer as follows for your consideration
Conditions and Commercial Terms
1). | Our quoted price not include any Bangladesh taxes ( AIT + VAT ).
2). | Our quotation based that received instruction from Mr Sarker.
And any Variation Work that is not shown in the our BOQ shall be consider as additional works.
3). | Our scope of work that Additional and Cancel Lighting Work at Office Building only.
4). | Our offer is based on Preparing materials around 2month and Construction schedule to be discus with m/s YKK.
5). | Application fee to the Bangladesh authority as Power, Fire, Envelopment is not included.
6). | Price Escalation Should there be any currency fluctuation of 5% or more, we request such adjustment to be made
payable to us.
7). | Validity period is 30days after submit quotation.
8). | Payment 30 days from receipt of invoice.
Our Best Offer is | US$ 20,000.00 | Not Include VAT
(US Dollar : Twenty Thousand Only).
We hope that our offer meets your budget. Please feel free to contact us if you have any queries
in regard to our offer. We look forward to be of service to you.
Yours faithfully,
Yuichi Akagi
Country Manager | MEMBER OF SUNTEC GROUP , JAPAN
SUNTEC IS ALSO KNOWN AS 'SANYO ENGINEERING & CONSTRUCTION INC.' IN OVER SEAS
[cover2]
Our Ref : SEC/BD/161112/00
QUOTATION
PROJECT : | YKK BANGLADESH FACTORY
Additional and Cancel Lighting Work at Office Building
CLIENT : | M/S. SHIMIZU CO.,LTD
DATE : | 12th. NOVEMBER 2016
SUBMITTED BY :
SANYO ENGINEERING & CONSTRUCTION INC.
BANGLADESH BRANCH
ADDRESS: BDBL BHABAN, 6th Floor, Plot #3, Bir-Uttam A.K. Khandakar Road,
Mohakhali C/A, Dhaka-1212, Bangladesh Tel: +88-029843361 Fax: +88-029843360
MEMBER OF SUNTEC GROUP , JAPAN
SUNTEC is also known as 'SANYO ENGINEERING & CONSTRUCTION INC.' in Over seas
[BOQ]
YKK BANGLADESH FACTORY
Additional and Cancel Lighting Work at Office Building | Our Ref : SEC/BD/161112/00 | 12th November, 2016
Item No. | Description | Unit | Q'ty | Foreign Material ( US$ ) | Local Material ( US$ ) | Local Labor ( US$ ) | Total Amount ( US$ ) | Remarks
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount
A | MECHANICAL WORKS
A-1 | LIGHTING SYSTEM
A-1-1 | Lighting Fixture w/o Led Tube | A22 Led22W*2 Open Refrector | Sets | 7.00 | 40.00 | 280.00 | N.A. | 8.70 | 60.90 | 48.70 | 340.90
A-1-2 | Lighting Fixture w/o Led Tube | B22 Led22W*2 V Shape | Sets | 12.00 | 44.00 | 528.00 | N.A. | 8.70 | 104.40 | 52.70 | 632.40
A-1-3 | Lighting Fixture w/o Led Tube | B21 Led22W*1 V Shape | Sets | 2.00 | 35.00 | 70.00 | N.A. | 7.61 | 15.22 | 42.61 | 85.22 | 間仕切り変更、非常灯から一般灯へ変更。
A-1-4 | Lighting Fixture | C94 Led9W*4 Recessed w/Al.Louver | Sets | 18.00 | 152.00 | 2,736.00 | N.A. | 13.05 | 234.90 | 165.05 | 2,970.90
A-1-5 | Lighting Fixture | G11 Led9W*1 Bracket w/Op.Acrylic cover | Sets | 15.00 | 40.00 | 600.00 | N.A. | 6.52 | 97.80 | 46.52 | 697.80
A-1-6 | Lighting Fixture | G21 Led22W*1 Bracket w/Op.Acrylic cover | Sets | 4.00 | 46.00 | 184.00 | N.A. | 6.52 | 26.08 | 52.52 | 210.08
A-1-7 | Lighting Fixture | D11 Led12.8W*1 Down light | Sets | 20.00 | 43.00 | 860.00 | N.A. | 7.61 | 152.20 | 50.61 | 1,012.20
A-1-8 | Lighting Fixture w/o Led Tube | E22 Led22W*2 Recess w/Al.Louver | Sets | 13.00 | 88.00 | 1,144.00 | N.A. | 8.70 | 113.10 | 96.70 | 1,257.10
A-1-9 | Lighting Fixture | H106 Led106W*1 Low bay | Sets | 1.00 | 621.00 | 621.00 | N.A. | N.A. | 621.00 | 621.00 | Only Supply to M/S YKK
A-1-10 | Lighting Fixture | H106 Led106W*2 Low bay | Sets | (5.00) | N.A. | N.A. | 7.61 | (38.05) | 7.61 | (38.05) | Only Supply to M/S YKK
A-1-11 | Lighting Fixture | ① Recessed Led Light 4tube | Sets | 4.00 | 205.00 | 820.00 | N.A. | 6.52 | 26.08 | 211.52 | 846.08
A-1-12 | Lighting Fixture | ② Wall Bracket Mounted Led Light Universal type | Sets | 10.00 | 293.00 | 2,930.00 | N.A. | 6.52 | 65.20 | 299.52 | 2,995.20
A-1-13 | Lighting Fixture | ③ Pin Light Led Light | Sets | 3.00 | 54.00 | 162.00 | N.A. | 6.52 | 19.56 | 60.52 | 181.56
A-1-14 | Lighting Fixture | ④ Cove Lighting Led Tape Type Led | Sets | 1.00 | 699.00 | 699.00 | N.A. | 6.52 | 6.52 | 705.52 | 705.52
A-1-15 | Lighting Fixture | ⑤ Recessed Type Led Light | Sets | 4.00 | 131.00 | 524.00 | N.A. | 6.52 | 26.08 | 137.52 | 550.08
A-1-16 | Lighting Fixture | ⑥ Wall Bracket Mounted Led Light Universal type | Sets | 4.00 | 246.00 | 984.00 | N.A. | 6.52 | 26.08 | 252.52 | 1,010.08
A-1-17 | Lighing Switch | w/Surface box | Sets | 1.00 | 0.42 | 0.42 | N.A. | 3.26 | 3.26 | 3.68 | 3.68
A-1-18 | Support Material | for Equipment | Lot | 1.00 | N.A. | 750.37 | 750.37 | 154.31 | 154.31 | 904.68 | 904.68
A-1-19 | Wire | THB 2.5sqmm | M | 2,136.00 | 0.37 | 790.32 | N.A. | 0.35 | 747.60 | 0.72 | 1,537.92
A-1-20 | for Above Cable Accessories | Lot | 1.00 | 17.47 | 17.47 | 3.99 | 3.99 | 24.42 | 24.42 | 45.88 | 45.88
A-1-21 | Conduit Pipe | EMT 1" Straight | Length | 104.00 | 11.80 | 1,227.20 | N.A. | 5.44 | 565.76 | 17.24 | 1,792.96
A-1-22 | Conduit Pipe | EMT 1" Coupling | Nos | 156.00 | 1.26 | 196.56 | N.A. | 0.87 | 135.72 | 2.13 | 332.28
A-1-23 | Conduit Pipe | EMT 1" Connector, Bushing | Nos | 240.00 | 5.46 | 1,310.40 | N.A. | 1.74 | 417.60 | 7.20 | 1,728.00
A-1-24 | for Above accessories | Lot | 1.00 | 299.40 | 299.40 | 68.42 | 68.42 | 183.75 | 183.75 | 551.57 | 551.57
A-1-25 | for Above support materials | Lot | 1.00 | N.A. | 708.24 | 708.24 | 427.85 | 427.85 | 1,136.09 | 1,136.09
A-1-26 | for Above Support Pinting | Lot | 1.00 | N.A. | 38.78 | 38.78 | 35.14 | 35.14 | 73.92 | 73.92
A-1-27 | Miscellaneous & Consumable | Lot | 1.00 | 371.23 | 371.23 | 34.20 | 34.20 | 78.52 | 78.52 | 483.95 | 483.95
A-1-28 | Transportation Equipment | Lot | 1.00 | 670.00 | 670.00 | 120.00 | 120.00 | 280.00 | 280.00 | 1,070.00 | 1,070.00
A-1-29 | Testing, Balancing & Commissioning | Lot | 1.00 | 99.00 | 99.00 | 9.00 | 9.00 | 44.00 | 44.00 | 152.00 | 152.00
SUB TOTAL A-1 | VENTILATION WORK | 18,124.00 | 1,733.00 | 4,034.00 | 23,891.00
A-2 | EMERGENCY AND EXIT SIGN SYSTEM
A-2-1 | Lighting Fixture w/o Led Tube | A22B Led22W*2 Open Refrector | Sets | (7.00) | 40.00 | (280.00) | N.A. | 8.70 | (60.90) | 48.70 | (340.90)
A-2-2 | Lighting Fixture w/o Led Tube | B22B Led22W*2 V Shape | Sets | (4.00) | 40.00 | (160.00) | N.A. | 8.70 | (34.80) | 48.70 | (194.80)
A-2-3 | Lighting Fixture | C94B Led9W*4 Recessed w/Al.Louver | Sets | (17.00) | 140.00 | (2,380.00) | N.A. | 13.05 | (221.85) | 153.05 | (2,601.85)
A-2-4 | Lighting Fixture w/o Led Tube | G21B Led22W*1 Bracket w/Op.Acrylic cover | Sets | (2.00) | 80.00 | (160.00) | N.A. | 7.61 | (15.22) | 87.61 | (175.22)
A-2-5 | Lighting Fixture | D11B Led12.8W*1 Down light | Sets | (8.00) | 40.00 | (320.00) | N.A. | 7.61 | (60.88) | 47.61 | (380.88)
A-2-6 | Lighting Fixture w/o Led Tube | E22B Led22W*2 Recess w/Al.Louver | Sets | (12.00) | 80.00 | (960.00) | N.A. | 8.70 | (104.40) | 88.70 | (1,064.40)
A-2-7 | Lighting Fixture | H106B Led106W*1 Low bay | Sets | (1.00) | 580.00 | (580.00) | N.A. | 7.61 | (7.61) | 587.61 | (587.61)
A-2-8 | Lighting Fixture | Exit Light Led10W*1 w/Battery | Sets | (18.00) | 43.82 | (788.76) | N.A. | 8.70 | (156.60) | 52.52 | (945.36)
A-2-9 | Support Material | for Equipment | Lot | 1.00 | N.A. | (693.88) | (693.88) | (108.77) | (108.77) | (802.65) | (802.65)
A-2-10 | Miscellaneous & Consumable | Lot | 1.00 | (132.24) | (132.24) | (15.12) | (15.12) | (15.97) | (15.97) | (163.33) | (163.33)
A-2-11 | Transportation Equipment | Lot | 1.00 | (240.00) | (240.00) | (54.00) | (54.00) | (60.00) | (60.00) | (354.00) | (354.00)
A-2-12 | Testing, Balancing & Commissioning | Lot | 1.00 | (35.00) | (35.00) | (4.00) | (4.00) | (9.00) | (9.00) | (48.00) | (48.00)
SUB TOTAL A-2 | VENTILATION DUCTING WORKS AND ACCS. | (6,036.00) | (767.00) | (856.00) | (7,659.00)
TOTAL A | 12,088.00 | 966.00 | 3,178.00 | 16,232.00
B | PRELIMINARIES
B-1 | SUPERVISION | Lot | 1.00 | 1,660.00 | 1,660.00 | N.A. | N.A. | 1,660.00 | 1,660.00
B-2 | SITE EXPENSES | Lot | 1.00 | 660.00 | 660.00 | N.A. | N.A. | 660.00 | 660.00
TOTAL B | 2,320.00 | 0.00 | 0.00 | 2,320.00
C | OVER HEAD | Lot | 1.00 | 1,448.00 | 1,448.00 | N.A. | N.A. | 1,448.00 | 1,448.00
GRAND TOTAL | 20,000.00