Govt. of the People’s Republic of Bangladesh
Prime Minister’s Office
Bangladesh Economic Zones Authority
Biniyog Bhaban (Level-7,8,9). E-6/B,
Agargaon, Sher-E-Bangla Nagar, Dhaka-1207
www.beza.gov.bd
Investment Priority
Record Number: 03.07.00.00.023.14.213.2023.1598 Date: 19 July 2026
SOP for Environmental Clearance Certificate
In exercise of the power conferred by sub-rule (2a) of rule 3 of the “One Stop Service
(Bangladesh Economic Zones Authority) Rules, 2018” read with Section 11 of the “One Stop
Service Act, 2018”, Bangladesh Economic Zones Authority hereby promulgates the following
Standard Operating Procedure, namely:
1. Title, Application and Introduction. – (1) These Standard Operating Procedure will be
known as the Standard Operating Procedure of the Environmental Clearance, Bangladesh
Economic Zone Authority
(2) These will come into force immediately
(3) It shall apply to economic zones established under the Bangladesh Economic Zones Act,
2010
2 . Objectives : The objectives of Environment Clearance:
a) Regulatory Compliance and Enforcement: Ensuring all industrial units within Economic
Zones comply with the Environmental Conservation Rules, 2023 (ECR’23) and Outline
specific requirements for different project categories (Green, Yellow, Orange, Red) to ensure
adherence to national environmental regulations.
b) Simplified Business Procedures: Providing a clear, step-by-step guide for investors to ensure
a smooth and efficient ECC application process and Facilitate ease of doing business by
minimizing regulatory burdens and ensuring transparency in environmental approval processes.
c) Alignment with National and International Standards: Align ECC processes with
national environmental policies and ensure that industries within the Economic Zones
contribute to broader climate goals and environmental commitments.
d) Comprehensive Environmental Assessment: Ensure a thorough evaluation of
potential environmental impacts through standardized assessments. Categorize projects
based on their environmental risk to facilitate appropriate review and mitigation
strategies.
3. Stage: The SOP for ECC applies to all prospective and existing investors who intend to
obtain an Environment Clearance Certificate for setting up or operating a business within the
Economic Zone. It covers the step-by-step application process, submission of required
documents, timelines for processing, and responsibilities of both the applicants and the
authorities. After getting Investment clearance and Land Lease ECC application process get
started.
4. Environmental Clearance
The coexistence of economic growth and environmental protection is fundamental in today’s
world for sustainable development. In accordance with this basic policy, the unit investor who
aims to enter the Economic Zone (EZ) should obtain Environmental Certificate Clearance
(ECC) based on Environmental Conservation Rules, 2023 (ECR’23). For the purpose of
issuance of Environmental Clearance Certificate, the industrial units and projects are, in
consideration of their site and impact on the environment, classified into the following four
categories:
• Green
• Yellow
• Orange
• Red
Industries and projects of each category are described in Schedule- 1 of ECR’23. The procedure
of obtaining ECC is different for each aforementioned category.
On the procedure of ECC for unit investor of the project in EZ, special processes which listed
below are applied.
→ Preparation and submission of Pollution Control Management (PCM) (for Green and
Yellow Category Projects/Industries), Initial Environment Examination (IEE)
Checklist for Orange Category is required to ensure the conservation of environment
around the EZ. For Red Category industries or projects, a detailed Environmental
Management Plan (EMP) report is a mandatory requirement for obtaining an
Environmental Clearance Certificate (ECC).
→ In case of preparing the EMP report for Red Category Projects or IEE Checklist for
Orange Category projects, unit investor can use environmental baseline data used in
EIA report of the corresponding Economic Zone or Environmental Monitoring data of
nearby industries within the same EZ. It is apparent that the Industrial Activities within
an Economic Zone cause degradation of Air Quality and depletion of Groundwater due
to excessive use by the industries. In accordance with that, the validity period of these
baseline data of Economic Zones has been considered to be 5 years.
→ A unit investor inside EZ can conduct temporary works before getting the ECC but it is
required to obtain ECC before the construction of main building.
Definitions
• Pollution Control Management (PCM) : The investors of Green and Yellow Category
projects and industries must submit a Pollution Control Management (PCM) for their
proposed Project/Industry. The contents of the Document Include:
o General information/ Project Profile
o Details of the Production Process with Process Flow Diagram
o Details of ETP/STP/WTP or any other waste management system
o Brief description of Mitigation Measures of projected Environmental Impacts
• Initial Environment Examination (IEE) Checklist: The investor of Orange Category
Projects and Industries must submit an Initial Environment Examination (IEE)
Checklist for their proposed industry and projects. The contents of the document will
include but not be limited to-
o General information/ Project Profile
o Details of the Production Process with Process Flow Diagram
o Details of pollutants (e.g. Effluent, Emissions etc.)
o Details of Infrastructure
o Waste management plan
o Details of ETP/STP/WTP
• Environmental Management Plan (EMP) : The investor of Red Category Projects and
Industries must submit an • Environmental Management Plan (EMP) for their
proposed industry and projects. An Environmental Management Plan (EMP) report is
a critical document that delineates strategies for minimizing and managing the
environmental impacts of a proposed industrial project. It assesses potential effects on
the environment across the project's lifecycle, including construction, operation, and
decommissioning phases. The contents of the document will include but not be limited
to-
o Introduction
o Project Description
o Environmental Policy
o Environmental Compliance Requirements
o Environmental Impacts and Mitigation Measures
o Environmental Surveillance, Monitoring and Auditing
o Contingency Planning
o Organizational Structure
o Budget and Implementation Program
Steps for completing Environmental Clearance Procedure for Green, Yellow, Orange and
Red Category Projects
Step 1- Online Submission of the required documents to the One Stop Service (OSS) along
with a PCM (for Green and Yellow) or IEE Checklist (For Orange) or EMP (For Red Category)
of the proposed project.
The required documents include:
✓ Fill up Form 3
✓ Feasibility Report / Project Profile
✓ Company Latest Documents (Like Trade license, TIN, VAT etc.)
✓ Letter of Investment Clearance from BEZA
✓ Layout Plan (including water treatment & Discharge locations)
✓ Process Flow Diagram
✓ Location Map
✓ Land Lease Agreement or Land Ownership Document or Land Allotment Letter
✓ Processing Fee + 15% VAT (As per schedule 6)
✓ ECC Application Fee + 15% VAT (As per schedule 7)
✓ Pollution Control Management (PCM) [For Green and Yellow Category], IEE
Checklist (For Orange) and EMP report (For Red Category) of the proposed project
Step 2 - Submission of the hard copies to BEZA OSSC along with supporting documents
Step 3 - Forwarding of the documents to the local DoE by BEZA
Step 4 - Site inspection by DoE
Step 5 - Issuance of ECC by DoE through online (Digital Certificate)
Step 6 - Upon receiving the ECC
Step 7 - Start of construction phase. Regular monitoring will be required to be conducted by a
third-party consultant appointed by the Investor.
Step 8 - Issued ECC will be subjected to renewal (for Green Category Projects/Industries,
renewal after each Five-years period and for Yellow Two- years and Orange, Red
Projects/Industries, renewal after each One-year period)
Step 9 - End of Construction phase and beginning of Operation phase.
Guideline for obtaining the Environmental Clearance Certificate for the Unit Investors
of Green, Yellow, Orange and Red Category projects
Particulars Environmental Clearance Procedure (Proposed)
Competent
Authority
Prime Minister’s Office
Ministry of Environment and Forests
Service
Window
Agency(s)
One Stop Service (OSS)
BEZA Office, Dhaka
Legal basis
(Including
applied
standard)
Bangladesh Economic Zones Act, 2010 (amendment, 2015)
Bangladesh Economic Zones Rules, 2014
Bangladesh Environmental Conservation Act, 1995 (ECA’95; amendment,
2010)
Bangladesh Environmental Conservation Rules, 2023
One Stop Service Act, 2018
One Stop Service Rules, 2018
Purpose An investor upon receiving an Investment Clearance from BEZA must
complete the environmental procedure and obtain an Environmental Clearance
Certificate from Department of Environment (DOE) before the start of
operation
Assessment
points
To ensure conformity of the Construction and Operation phase of the project
with all the relevant Acts and Rules as well as to raise environmental awareness
among the investors and to minimize damage to the environment.
Online
Application
Online application and offline application
Required
Documents for
Obtaining
Environmental
Clearance
Certificate
from DOE
Green
1. Fill up Form 3
2. Feasibility Report / Project Profile
3. Company Latest Documents (Like Trade license,
TIN, VAT etc.)
4. Letter of Investment Clearance from BEZA
5. Layout Plan (including water treatment & Discharge
locations)
6. Process Flow Diagram
7. Location Map
8. Land Lease Agreement or Land Ownership
Document or Land Allotment Letter
9. Processing Fee + 15% VAT (As per schedule 6)
10. ECC Application Fee + 15% VAT (As per schedule
7)
11. Pollution Control Management (PCM)
Yellow
1. Fill up Form 3
2. Feasibility Report / Project Profile
3. Company Latest Documents (Like Trade license,
TIN, VAT etc.)
4. Letter of Investment Clearance from BEZA
5. Layout Plan (including water treatment & Discharge
locations)
6. Process Flow Diagram
7. Location Map
8. Land Lease Agreement or Land Ownership
Document or Land Allotment Letter
9. Processing Fee + 15% VAT (As per schedule 6)
10. ECC Application Fee + 15% VAT (As per schedule 7)
11. Pollution Control Management (PCM) [Prescribed
Format]
Orange
1. Fill up Form 3
2. Feasibility Report / Project Profile
3. Company Latest Documents (Like Trade license,
TIN, VAT etc.)
4. Letter of Investment Clearance from BEZA
5. Layout Plan (including water treatment & Discharge
locations)
6. Process Flow Diagram
7. Location Map
8. Land Lease Agreement or Land Ownership
Document or Land Allotment Letter
9. Processing Fee + 15% VAT (As per schedule 6)
10. ECC Application Fee + 15% VAT (As per schedule 7)
11. IEE Checklist (As per prescribed Format)
Red
1. Fill up Form 3
2. Feasibility Report / Project Profile
3. Company Latest Documents (Like Trade license,
TIN, VAT etc.)
4. Letter of Investment Clearance from BEZA
5. Layout Plan (including water treatment & Discharge
locations)
6. Process Flow Diagram
7. Location Map
8. Land Lease Agreement or Land Ownership
Document or Land Allotment Letter
9. Processing Fee + 15% VAT (As per schedule 6)
10. ECC Application Fee + 15% VAT (As per schedule
7)
11. EMP report (As per Schedule 11 of ECR’ 23) [need
to add with impact analysis report if no CETP inside
EZ]
Actual
procedure
1. After obtaining Letter of Investment Clearance from BEZA, the investors
must submit all the required Documents (See “Required Documents for
ECC Row”) in English to the OSS online portal to start the procedure for
Environment Clearance.
2. After the successful online submission, the investor should submit 3 sets of
hard copy with all necessary documents in BEZA OSSC. BEZA OSS must
pre-assess the documents before the official submission.
3. The documents will then be forwarded to the DoE local office from BEZA
OSS to proceed with the procedure for obtaining an ECC.
4. DoE will then make an assessment of the submitted documents and conduct
a site inspection if needed.
5. If all the documents meet DoE’s Standard, DoE will issue an
Environmental Clearance Certificate via online (Digital Certificate).
6. After getting the ECC, the investor is allowed to start the construction of
the project.
7. Regular monitoring is required during the construction period and the
monitoring reports must be submitted to DoE.
8. Upon completion of construction, the investor is allowed to start the
operation.
9. Environmental Clearance Certificate is subjected to renewal after a certain
interval; Five -year period for Green Category and two-year period for
yellow category and one year period for Orange & Red- Category Projects
and Industries.
Processing
timeframe From the day of application-
Green- 07 working days to obtain ECC
Yellow- 07 working days to obtain ECC
Orange- 20 working days to obtain ECC
Red- 30 working days to obtain ECC
Application
Fees
1. Processing Fee + 15% Government imposed VAT
Category Processing Fee
(BDT)
VAT (BDT)
Yellow 2000 300
Orange 5000 750
Red 10000 1500
2. Application Fee + 15% Government imposed VAT (Depends on the
estimated total amount of Investment)
1 Lac to 5 Lac 3,000
5 Lac 1 to 10 Lac 6,000
10 Lac 1 to 50 Lac 10,000
50 Lac 1 to 1 Crore 20,000
1 Crore 1 to 5 Crore 40,000
5 Crore 1 to 20 Crore 80,000
20 Crore 1 to 50 Crore 160,000
50 Crore 1 to 100 Crore 2,40,000
100 Crore 1 to 200 Crore 4,00,000
200 Crore 1 to 500 Crore 6,00,000
500 Crore 1 to 1000 Crore 8,00,000
1000 Crore 1 to 20000 Crore 10,00,000
More than 20000 Crore 1 15,00,000
Payment
Method
Processing / ECC Fee
(A Challan Codes)
Ministry / Organization
Code- 14503
Economic Code- 1422319
VAT Fee (15% of the
processing fee / ECC Fee)
(A Challan Codes)
Ministry / Organization Code- It
depends on the submitting DoE
office location.
VAT Code- 1141101
Remarks
• Currently the payment method is offline (Through A-Challan). But online
payment procedure is under development. When the online payment method
is developed, the investor can pay through BEZA OSS online portal while
applying online.
• The Investors of Treatment Facilities will be highly encouraged to adopt a
“Zero Discharge Policy” for the Treatment Facilities, especially for an Effluent
Treatment Plant (ETP).
Required documents for
Online Application:
• Fill up Form 3
• Feasibility Report / Project
Profile
• Company Latest Documents
(Like Trade license, TIN, VAT
etc.)
• Letter of Investment
Clearance from BEZA
• Layout Plan (including water
treatment & Discharge
locations)
• Process Flow Diagram
• Location Map
• Land Lease Agreement or
Land Ownership Document or
Land Allotment Letter
• Processing Fee + 15% VAT (As
per schedule 6)
• ECC Application Fee + 15%
VAT (As per schedule 7)
• Pollution Control
Management (PCM)
Required documents for
Online Application:
• Fill up Form 3
• Feasibility Report / Project
Profile
• Company Latest Documents
(Like Trade license, TIN, VAT
etc.)
• Letter of Investment
Clearance from BEZA
• Layout Plan (including water
treatment & Discharge
locations)
• Process Flow Diagram
• Location Map
• Land Lease Agreement or
Land Ownership Document or
Land Allotment Letter
• Processing Fee + 15% VAT (As
per schedule 6)
• ECC Application Fee + 15%
VAT (As per schedule 7)
• Pollution Control
Management (PCM)
Required documents for
Online Application:
• Fill up Form 3
• Feasibility Report / Project
Profile
• Company Latest Documents
(Like Trade license, TIN, VAT
etc.)
• Letter of Investment
Clearance from BEZA
• Layout Plan (including water
treatment & Discharge
locations)
• Process Flow Diagram
• Location Map
• Land Lease Agreement or
Land Ownership Document
or Land Allotment Letter
• Processing Fee + 15% VAT (As
per schedule 6)
• ECC Application Fee + 15%
VAT (As per schedule 7)
• IEE Checklist (As per
prescribed Format)
GREEN
Construction of the Project
Site Inspection by DoE
PROCEDURE FOR ISSUANCE ENVIRONMENTAL CLEARANCE CERTIFICATE FOR EZ UNIT
INVESTORS FOR GREEN, YELLOW, ORANGE AND RED CATEGORY PROJECTS
Online Submission of Documents to BEZA through OSS
Obtaining ECC through Online (Digital Certificate)
Beginning of Operation Phase
Environmental Clearance Renewal
after each one-year period
Environmental
Clearance Renewal
after each five-year
period
Forwarding of Application for ECC to the DoE with all required Documents
End of Construction Phase
YELLOW ORANGE RED
Required documents for
Online Application:
• Fill up Form 3
• Feasibility Report / Project
Profile
• Company Latest Documents
(Like Trade license, TIN, VAT
etc.)
• Letter of Investment
Clearance from BEZA
• Layout Plan (including water
treatment & Discharge
locations)
• Process Flow Diagram
• Location Map
• Land Lease Agreement or
Land Ownership Document
or Land Allotment Letter
• Processing Fee + 15% VAT (As
per schedule 6)
• ECC Application Fee + 15%
VAT (As per schedule 7)
• EMP report (As per Schedule
11 of ECR’ 23) [ need to add
with impact analysis report if
no CETP inside the EZ]
Submission of hard copies to BEZA OSSC
Environmental
Clearance Renewal after
each two-year period
Guideline for obtaining the Renewal of Environmental Clearance Certificate for the Unit
Investors of Green, Yellow, Orange and Red Category projects
Particulars Environmental Clearance Procedure (Proposed)
Competent
Authority
Prime Minister’s Office
Ministry of Environment and Forests
Service Window
Agency(s)
One Stop Service (OSS)
BEZA Office, Dhaka
Legal basis
(Including
applied standard)
Bangladesh Economic Zones Act, 2010 (amendment, 2015)
Bangladesh Economic Zones Rules, 2014
Bangladesh Environmental Conservation Act, 1995 (ECA’95;
amendment, 2010)
Bangladesh Environmental Conservation Rules, 2023
One Stop Service Act, 2018
One Stop Service Rules, 2018
Purpose An investor upon receiving an Environmental Clearance Certificate
(ECC) must follow the instructions of the ECC and need to renew it
periodically as per the environmental category.
Assessment points To ensure conformity of the Construction and Operation phase of the
project with all the relevant Acts and Rules as well as to raise
environmental awareness among the investors and to minimize damage
to the environment.
Online Application Online application and offline application
Required
Documents for
Obtaining
Environmental
Clearance
Certificate
from DOE
Green, Yellow, Orange, and Red 1. Fill up Form-5
2. Company latest documents
3. Location Map
4. Layout Plan (including water treatment & Discharge
locations)
5. Process Flow Diagram
6. Land Ownership Documents
7. Investment Clearance from BEZA
8. Old ECC Copy
9. Fire License (In case of running industry)
10. ECC Renewal Fee + 15% VAT (As per schedule 7)
11. Environmental monitoring report (If it is given in the ECC
condition)
Actual procedure 1. The investor needs to apply online through BEZA OSS online portal.
2. After the successful online submission, the investor should submit 3
sets of hard copy with all necessary documents in BEZA OSSC.
BEZA OSS must pre-assess the documents before the official
submission.
3. The documents will then be forwarded to the DoE local office from
BEZA OSS to proceed with the procedure for obtaining an ECC.
4. DoE will then make an assessment of the submitted documents and
conduct a site inspection if needed.
5. If all the documents meet DoE’s Standard, DoE will renew the
Environmental Clearance Certificate via online (Digital Certificate).
Processing
timeframe From the day of application-
Green- 07 working days to obtain ECC Renewal
Yellow- 07 working days to obtain ECC Renewal
Orange- 20 working days to obtain ECC Renewal
Red- 30 working days to obtain ECC Renewal
Application Fees Renewal Fee + 15% Government imposed VAT (Depends on the
estimated total amount of Investment)
1 Lac to 5 Lac 1,500
5 Lac 1 to 10 Lac 3,000
10 Lac 1 to 50 Lac 5,000
50 Lac 1 to 1 Crore 10,000
1 Crore 1 to 5 Crore 20,000
5 Crore 1 to 20 Crore 40,000
20 Crore 1 to 50 Crore 80,000
50 Crore 1 to 100 Crore 1,20,000
100 Crore 1 to 200 Crore 2,00,000
200 Crore 1 to 500 Crore 3,00,000
500 Crore 1 to 1000 Crore 4,00,000
1000 Crore 1 to 20000 Crore 5,00,000
More than 20000 Crore 1 7,50,000
Payment Method
ECC Renewal Fee
(A Chalan Codes)
Ministry / Organization
Code- 14503
Economic Code- 1422319
VAT Fee (15% of ECC
Renewal Fee)
(A Chalan Codes)
Ministry / Organization Code-
It depends on the submitting
DoE office location.
VAT Code- 1141101
Remarks
• Currently the payment method is offline (Through A-Challan). But
online payment procedure is under development. When the online
payment method is developed, the investor can pay through BEZA OSS
online portal while applying online.
Required documents for Online Application:
• Fill up Form-5
• Company latest documents
• Location Map
• Layout Plan (including water treatment & Discharge locations)
• Process Flow Diagram
• Land Ownership Documents
• Investment Clearance from BEZA
• Old ECC Copy
• Fire License (In case of running industry)
• ECC Renewal Fee + 15% VAT (As per schedule 7)
• Environmental monitoring report (If it is given in the ECC condition)
GREEN
Site Inspection by DoE
PROCEDURE FOR ISSUANCE RENEWAL OF ENVIRONMENTAL
CLEARANCE CERTIFICATE FOR EZ UNIT INVESTORS FOR GREEN,
YELLOW, ORANGE AND RED CATEGORY PROJECTS
Online Submission of Documents to BEZA through OSS
Obtaining ECC Renewal through Online (Digital Certificate)
Forwarding of Application for ECC to the DoE with all required
Documents
YELLOW ORANGE RED
Submission of hard copies to BEZA OSSC
List of All Forms
Form No. Name
FORM ENV-Online-1 Online Application Form through BEZA OSS online portal for ECC
FORM ENV-Online-2 Online Application Form through BEZA OSS online portal for ECC
Renewal
FORM ENV--3 Application Form for Environmental Clearance Certificate (Form-3)
FORM ENV-5 Application Form for Environmental Clearance Renewal
Application Forms for Environmental Procedure
Online Application Form through BEZA OSS online portal for ECC
[FORM ENV-online-1]
Online Application Form through BEZA OSS online portal for ECC Renewal
[FORM ENV-Online-2]
Application Form for Environmental Clearance Certificate
[FORM ENV-3]
Application for Environmental Clearance
For Industrial Establishment
To
---
----
Sir,
I hereby submit the following information for my proposed industrial establishment/ existing
establishment for the application of site clearance/ environmental clearance certificate.
1. Industrial Name:
a. Locational address of the industry :
b. Present address of the office :
2. (A) Proposed industrial establishment
i. Potential Project cost:
ii. Amount of land:
iii. Probable date of commencement of construction:
iv. Probable date of end of construction
v. Probable date of trial production of industrial establishments:
(B) Existing industry
i. Probable date of trial production of industrial establishments:
ii. Total investment amount:
3. Whether the proposed project falls within the ecologically sensitive area or the restricted area
mentioned in Schedule 9:
4. Name and quantity of the produced product (day/month/year):
5. (a) Name and quantity of raw materials (day/month/year):
(b) Source of raw materials:
6. (a) Daily total usage of water:
(b) Source of water:
7. (a) Name and quantity of fuel (day/month/year):
(b): Amount of electricity consumption (kwh) and source of electricity:
8. (a) Location map of industrial establishment :
(b) Lay out plan ( where applicable, the location of the waste treatment plant is indicated) :
9. (a) Description of the manufacturing process:
(b) Flow diagram of production process:
10. (a) Nature of solid waste :
(b) Daily possible amount of solid waste:
11. (a) Daily possible amount of liquid waste:
(b) Discharge point of liquid waste:
12. Nature of gaseous pollutants and its mode of emission:
13. Possible source of sound pollution and mitigation management :
14. Solid waste management system:
15. Liquid waste treatment system ( if necessary)*:
16. Air pollution control system ( if necessary)**:
17. Measures adopted for occupational health protection and safety :
18. Land schedule and mouza map:
19: Permission letter from RAJUK/ Chattogram Unnoyan Kortripokkho/ Khulna Unnoyan
Kortripokkho/ Rajshahi Unnoyon Kortripokkho/ Local Government ( if necessary):
20. (a) Scope of preliminary Environmental survey report/ Environmental impact assessment
report ( if necessary) :
(b) Environmental management plan ( if necessary) :
21. Feasibility study report ( if necessary) :
22. Others important information ( if necessary) :
Name of the entrepreneur (with seal)
Name:
Address:
Phone:
Email:
Date:
Declaration :
I, hereby declare that, the information given in the application form is true to the best of my
knowledge and no information has been concealed or distorted.
Name of the entrepreneur and signature
Note:
*Need to submit liquid waste treatment documents according to schedule 12.
**Submit air pollution control management documents.
*** Each page should bear the signature and seal of the entrepreneur or his representative.
Application Form for Environmental Clearance Certificate
[FORM ENV-5]
Application for renewal of environmental clearance certificate
To
----
----
Sir,
I hereby submit the following information for my existing establishment for the application of
renewal of environmental clearance certificate :
1. Name of industry/ project :
2. Industry/ Project address:
3. (a) Name and amount of produced products in case of industry (daily/monthly):
(b) Main activities of project in case of project:
4. Environmental clearance issue number: --------- Date:
5. Date of last renewal :------- date of expire:
6. Total amount of investment: -------- tk
7. Payable amount for clearance renewable fee:
Tressure challan no: Date:
Bank name: Brunch:
8. Payable amount for VAT on renewable of clearance:
Tressure challan no: Date:
Bank name: Brunch:
9. Factory or project activities:
Factory or project activities O Active O Close If close, Date of closing
-------/---/
Is there any change in the
production of factory
O Yes O No If yes, please mention
information below
10. Waste generate due to factory production process or project activities:
Waste type Waste description Amount(…../daily)
General solid waste
Liquid waste
Gaseous waste
Hazardous waste
Others waste
11. Liquid waste treatment ( if necessary ):
ETP Capacity ---m3/day Type of ETP O Chemical
O Bio
chemical
O Biological
O Others
Flow meter
Today’s date Today’s reading Total flow (m3)
Previous date Previous
reading
Sludge management
generate from
Dewatering O
Storage O
Abandoned O
Liquid waste final discharge O
ETP efficiency O Ongoing ETP O Close ETP
12. Result of liquid waste analysis ( if necessary): Latest result must be attached.
13. Air control management:
Gaseous
discharge
point
O boiler ( Fuel:
coal/diesel/gas)
Farness/smelter O Pulverization/ grinding
O buffing ( metal
polishing)
O acidic fume O mixing/ material handling
O cooking/ kitchen
emission
O O
Air
pollution
control
O chimney ( height
from base … meter)
O wet scrubber / ESP O Dust collector ( bag filter/
cyclone)
O channelization; hood, ducting
and suction management
O controlling management: cyclone/ wet
scrubber
O surrounded from
all side
O water spray
O dry extraction cum
bag filter
O closed belt conveyor
14. Analytical result of gaseous emission ( if necessary) : Attachment of latest result
15. Noise pollution management ( if necessary) :
Source of noise pollution O
O
O
O
Noise pollution control
management
Measured noise level O Latest result attached
16. others waste management:
Solid waste
management
O Dumping/ land
filling
O Reuse
O Composting
O sell
O
O control incineration
O Burn
O
Sewage management O Septic tank
O STP
O Disposal into
public sewage
system
O
O
17. Occupational health and safety :
Usage of
personal safety
equipment
O Boots
O Helmet
O dust mask/
respiratory mask
O safety glass
O First aid
O
O
O Apron/
suitable dress
O hand gloves
18. Zero discharge plan:
Is zero discharge plan
approved?
O Yes O No
If zero discharge plan is
approved
O Approval Date O End of implementation
Date:
Description of zero discharge
implementation plan
I, hereby declare that, the information given in the application form is true to the best of my
knowledge and no information has been concealed or distorted.
Name of the entrepreneur (with seal)
Name:
Address:
Phone:
Email:
Date:
Note:
*Applicant will sign every page of this form and attached documents