Environmental Clearance Certificate for Yellow Category
Sl. No. | Documents | Explanation of Documents | Time Frame | Fees | Remarks
1 | Pollution Control Management (PCM) | BEZA prescribed form | Within 45-60 to working days | Depends on the estimated total amount of Investment | Will be given by Nippon Koei
2 | Form 3 | DoE prescribed form | Will be given by Nippon Koei
3 | Forwarding Letter | Application to DoE | TCF will do.
4 | Authorization Letter | Appointment of Authorized person | TCF will do.
5 | BEZA Investment Clearance Certificate | BEZA approved ICC | Issued by BEZA
6 | Trade License | BEZA approved TL | Issued by BEZA
7 | Land use plan | BEZA approved Land Use Plan | Issued by BEZA
8 | Lease agreement | BSEZ and Artnature lease agreement | TCF has.
9 | Agreement with third party for collecting waste | Agreement with waste management company | Need to make an agreement with a third party for waste management.
10 | Location Map | General map of the project site indication the noticeable establishment around the project site. | Will be given by Nippon Koei
11 | Layout Plan of the project | Layout plan of the Artnature Factory | Given by Contractor SHIMIZU
12 | Drainage Plan of the project | Utility connection plan | Given by Contractor SHIMIZU
13 | Vicinity map | Vicinity map with number of building outline | Given by Contractor SHIMIZU
14 | Approved Master plan (BSEZ) | Approved Layout plan of the BSEZ | Given by Contractor SHIMIZU
15 | Details of the Production Process with Flow Diagram | Process of production flow with explanation | TCF has.
Note: Need to apply through BEZA OSSC.
[Quotation Summary ]
Environment Clearance quotation summary
Sl. No. | Name of Company | Price | Website | Remarks
1 | AGS Consulting | 375,000.00 | https://www.agsqa.net/ | Company dose not understand properly
2 | BUREAU VERITAS (BANGLADESH) PRIVATE LIMITED | 1,035,000.00 | https://www.bureauveritas.com.bd/
3 | VIRID Associate | 6,75,000.00 | https://viridassociate.com/
Note: We are searching for more quotation
[Schedule ]
Environmental Clearance Certificate for Yellow Category
Sl. No. | Particulars | Duration | Due Date
1 | Preparation of Documents | 10 days | 10-Jul-24
2 | Signature and Courier | 5 days | 15-Jul-24
3 | Online Application and Hard Copy Submission | 3 Days | 18-Jul-24
4 | Site Visit by DoE officials | 10 days | 28-Jul-24
5 | DoE Meeting | 10 days | 7-Aug-24
6 | Follow up DoE for ECC | 20 days | 27-Aug-24