Steps Process/Flow Due Date Completion Date Duration Status
1 必要書類・情報の共有
Collection of information and Required Documents 5-Jan-25 N/A
2 手続き必要書類の作成
Drafting Document 12-Jan-25 1 Week
3 署名手配
Signature 26-Jan-25 2 Weeks
4 公証・認証・発送
Notarization Application & Courier 23-Mar-25 8 Weeks
5 外務省からの検査(バングラデシュ)
MOFA Verification 6-Apr-25 2 Weeks
6 登記所へのオンライン申請
RJSC Online Application 7-Apr-25 1 Week
7 原本の提出
Hard Copy Submission to RJSC 14-Apr-25 1 Week
8 登記所への進捗確認
Follow up RJSC 14-May-25 1 Months
9 承認後書類の取得
Obtain Certified Copy 17-May-25 3 Days
10 中央銀行への報告
'Informing Bangladesh Bank 24-May-25 1 Week
業務報告書
Weekly Business Report
業務名:株式譲渡&代表者変更手続き業務
Name of Service: Share Transfer & Directorship Change
Share Transfer & Directorship Change
Notes:
1. This is an assumed timeline.
2. Based on situation and Authorities response the expected time may be increase or decrease.
Thank you very much for your consideration.
Thanks for being with TCF
Collection of
information
and Required
Documents
Drafting
Document Signature
Notarization
Application &
Courier
MOFA
Verification
RJSC
Application &
Submission
Follow up
RJSC
Obtain
Certified Copy
Informing
Bangladesh
Bank